(1)(a) In 2009, the Giyani area was officially declared a disaster zone as a result of terrible water and waste water situation. It was consequently adopted into the Presidential Siyahlola Programme. To redress the situation in Mopani, I issued an emergency directive in August 2014 to my Department’s Implementation Agent, i.e. Lepelle Northern Water to regularise water and sanitation provision in the Mopani District area.
In implementing the Directive, various projects were identified, categorised and prioritised in the Short - term/ critical emergency projects and the Medium - Long term projects as follows:
In addressing the medium to long term and the sustainability of the Mopani area and its surroundings, a number of projects were identified. The identified projects are in different stages of planning and designs and implementation, such as:
(1)(b) Over and above the designs and the implementation of the short-term/ critical emergency projects, Lepelle Northern Water is currently undertaking the Operation and Maintenance on existing and new infrastructure in Giyani Town which include material and/or equipment purchasing to refurbish dilapidated infrastructure.
The specified operation and maintenance is on-going as and when required on site to maintain the existing and new infrastructure until handed over to the Water Service Authority.
(2)(a) The contractor appointed by Lepelle Northern Water is LTE Consulting on a Turnkey basis for the project.
(2)(b) The approved budget for the Mopani Intervention project is R2.2 billion. Out of the approved budget an amount of R1 391 838.00 has been spent to date which include the amount of R57 million of the specified project i.e. operation and maintenance for the planning, designs and implementation of the Mopani Intervention project.
(2)(c) As indicated above, the short–term/ critical emergency projects have since been completed. The medium-long term projects are various planning, designs and implementation stages. The specified operation and maintenance is on-going as when required on site to maintain the existing and new infrastructure before is handed over to the Water Service Authority.
(3) Due to the emergency situation and the urgency to redress the water and sanitation in Mopani area the project did not go through the open tender process. However, the appointment of the Service Provider was completed through the close tender process using Department Panel. The specified project of operation and maintenance is part of the Mopani Intervention programme. As indicated in (2) above, LTE Consulting was appointed on a Turnkey basis for the project. We are convinced that the method used to appoint LTE Consulting is in line with SCM policy and National Treasury guidelines applicable to emergency/disaster situations.