(1) The Municipalities benefiting from the Accelerated Community Infrastructure Programme in Mpumalanga are the following:
(2) Refer to the table below for the Nature of projects, cost and timeframe for each of the specified municipalities:
Municipality |
Nature of the Project/Project Name/ |
Cost /Budget allocated for the Financial Year 2016/2017 |
Time frame |
Emakhazeni LM |
Refurbishment of Waterval Boven WWTW and Booster pump stations |
R6 365 000 |
6 Months (March-Nov) |
Emakhazeni LM |
Refurbishment of Belfast WWTW and Booster pump stations |
R8 567 000 |
6 months (March- Nov) |
Emakhazeni LM |
Refurbishment of Machadodrop WWTW |
R2 000 000 |
6 months (March-Nov) |
ThabaChweu LM |
Refurbishment of Lydenburg WWTW |
R7 731 000 |
6 months (March- Nov) |
Dr PixleykaSeme LM |
Refurbishment of Amersfoort WWTW and Booster pump stations |
R3 302 000 |
6 months (March -Nov) |
Total |
R27 965 000 |
---00O00---