1. During the Fourth Quarter of the 2018-19 financial year there were no expenditure incurred on the development of the Rail Safety Bill and therefore there was no reporting.
2. The Railway Safety Bill was submitted to Cabinet (a) on 7 February 2018 and (b) approved for public consultation.
3. (a) Work on the development of the Railway Safety Bill commenced on 15 September 2015 and was concluded on 31 March 2019.
(b) The Railway Safety Bill has been developed.
(c) (i) The specialist drafting of the Bill was assigned to external contractors
(ii) R2,421,796-62