- The project was under the Sakhabakhi programme of the Department. - The duration of the project was from 29 November 2010 to 30 January 2011. - Total budget of the project was R1 532,132.20 which had a total expenditure of R 482,409.69 at the time of the visit. - The daily wage rate that was given to beneficiaries was R70 - A total of 18 work opportunities were created, 6 women, 12 youth and no disabled persons. - The aim of the project was to renovate 16 dilapidated classrooms, make classrooms habitable, create a conducive learning environment and encourage learners to attend school in all weather conditions. - No training had been conducted for the labourers and though there was a need for training, time did not allow for training since the project lasted for only two months.