|No |Project |GO / NO GO | |1. |Pilot 500 SWH rollout then proceed to|GO-Pilot implementing | | |mass roll-out overtime | | |2. |Assist DOE in SWH roll-out plans |GO - assigning and aligning with | | | |DOE plans | |3. |Develop feasibilities in potential |GO-starting process with 2 key | | |investment in loca lSWH manufacturing|local/Chinese technology partners | | |facilities | | |4. |Flaring on 2 Landfill gas sites in |NO GO-Project progressed but ETA | | |Nelson Mandela Bay Metropolitan |not defined as an IPP thus Project| | |Municipality (NMBMM) |cancelled by Municipality | |5. |Installation of 400,000 CFLs |NO GO-cost recovery analys is | | | |underway | |6. |Installation of 35,000 Streetlights |NO GO-cost recovery analys is | | |in NMBMM |underway | |7. |25MW windproject in NMBMM |NO GO-possible dispute with | | | |contractor-plans to prepare case | |8. |Waste Water Treatment Project in |NO GO-cost recovery analysis | | |NMBMM |underway | |9. |Hydro opportunities in EasternCape |NO GO-no defined project ever | | | |identified |