The completion date that the Department had received from the DBSA as the implementing agent on 30 November 2011 showed that some schools would be completed at the end of March 2012 and some at the end of June 2012. However, the latest submission received on Monday, 23 January 2012 from the DBSA showed that the completion date would be August 2012. The sites were handed over to contractors on the 12 and 13 January 2012. The Department committed that it would engage the DBSA further to ascertain whether or not this latest target for the completion of the schools would be met.