. At three facilities in KwaZulu-Natal, projects were completed and furniture and equipment delivered, however, the facilities were not used immediately as staff was not made available by the provincial Department of Health. Although a unit within a facility was completed on 18 September 2007, it was only commissioned on 6 January 2009, which is 1.4 years after its completion.