. In Gauteng, the Provincial Department of Basic Education's failure to synchronise the procurement of library and computer related resources with infrastructure delivery timetables resulted in, as at 31 March 2009, computer rooms and libraries of ten schools not being used. . In Free State, computer rooms at the Atang Primary School were not used, as equipment was unavailable at the date of commissioning. The Provincial Department of Basic Education did not report on the project's progress to the district office in time for them to budget for and procure the required equipment. . During a visit in July 2008 at the Ekuthuleni Primary School in the Western Cape, the audit team determined that the library had not been used since the school was commissioned in 26 January 2006. According to the principal, the resources for the library had been ordered two months prior to the initial completion of the school in November 2005, but had not been delivered. A visit to the school on 31 January 2011 (five years after commissioning) revealed that the library was still not fully utilised. Books in the library were donated by a charity organisation, but books ordered by the Department had not been provided.