Eskom build programme (as end of 2011) . Medupi is 35% complete, with 56.9% of the budget having being spent. . Kusile is 17% complete, with 30% of the budget having being spent. . Ingula is 41% complete, with 54.3% of the budget having being spent. . The Return to Service programme is 93.5% complete, with 89% of the budget having being spent. . Transmission projects are more than 70% complete, with 70.4% of the budget having being spent.