. 91% of the Inyaka Water Treatment Works was completed against a target of 98%; . On the Nandoni Water Distribution Network and Water Treatment Works, its achievement is 58% against a target of 79%; and . On the construction of the Nandoni Pipeline, its performance is 20% against a target of 27%. For Hluhluwe, the Department's percentage progress exceeded the targeted percentage by 1% (93% versus the target of 92%).