1. Long-term infrastructure plan. The Department receives approximately R3 billion for capital works over the MTEF to enhance access to justice: R 1.03 billion in 2012/13; R1.08 billion in 2013/14; and R1.14 billion in 2014/15. The Committee is interested that the Strategic Plan now includes an infrastructure plan, although some of the data that it contains appears contradictory (for example, the Lutzville Periodical Court is reported as handed over with a total project cost of R11.8 million but over the MTEF the following amounts are budgeted for: R6.1 million in 2013/14; R0.7 million in 2014/15; and R36.6 million in 2015/16). The Ntuzuma Magistrate's Court officially opens on 28 May 2013. The construction of the new Limpopo High Court in Polokwane began in February 2010 and was due for completion in July 2012 but is not on track. The most recent projections are that the Court will be completed next year with a total cost of R460 million. The new Mpumalanga High Court in Nelspruit is being planned and is due to be implemented in 2013/14.