a) The following progress has been made:
PROGRESS FOR THE EMERGENCY UNIT
The technical work for the Emergency Unit is 99% complete. The Certificate of Occupancy has been issued by the City of Johannesburg. The clinical operations will be executed in phases starting from the 6th May 2022.
PROGRESS FOR THE REMEDIAL WORK FOR ALL THE BLOCKS
The remedial work covers the following milestones:
(i) THE IMPLEMENTATION OF THE NEW STORES FACILITY
(ii) CONDUCTING OF A DETAILED ASSESSMENT
Construction works will start on the 4 April 2022 until 13 June 2022
(iii) THE IMPLEMENTATION OF A TEMPORARY ACCESS TO PARKING
(iv) THE IMPLEMENTATION OF THE MAIN WORK FOR BLOCK 4 AND 5 REMEDIAL WORKS
b) Practical handover and completion is December 2023
END.