The Final Report of the Auditor-General indicated that there was a misstatement on the Barberton project. An amount of R24 784 279 was classified as capital work in progress instead of infrastructure project asset completed.
The department also appointed an independent quantity surveyor to establish the value of the asset and the report indicated the following:
Project |
Barberton Tourism and Biodiversity Corridor |
|
Project Number |
DEAT1/2000/1705 |
|
Implementer |
Barberton Chamber of Business |
|
Construction Period |
04/06/2010 - 30/06/2014 |
|
Location |
Barberton Mpumalanga |
|
Business Plan Value |
R 24 784 279,00 |
|
Assessed Value |
R 27 784 279,00 |
|