- The objective of the project was to control water flow during the rainy season and minimise flooding in residential areas. - The project duration was six months, from 13 September 2010 to 13 April 2011. - Since the project started, it created 20 work opportunities. - The project employed three adult males, four adult females, six male youth, seven female youth and no persons with disabilities. - The number of people employed was expected to increase at the stage of installation of kerbs and the construction of concrete v-drains. - The project was behind schedule due to rainfall. - Total expenditure at the time of the visit was at 30.31% (R1,176,051.95). - Training conducted focused on technical skills transfer and social issues, technical training on concrete work, kerb laying, social issues and AIDS awareness courses.