2.3.3 The contract, initially valued at R315,6 million, was awarded on 3 October 2008, and was scheduled for completion by 2 June 2010. As projected in March 2011, the centre was eventually completed in September that year. At the time of the visit, however, the date for it becoming fully operational was still unknown owing to IT installations that had not been completed.