(1) With reference to the Accelerated Schools Infrastructure Delivery Initiative programme,
(a) (i) Number of inappropriate school completed in 2014-15 is 59
(ii) Number of inappropriate school completed in 2015-16 is 52
(iii) Number of inappropriate school completed in 2016-17 is 16
(iv) Number of inappropriate school completed in 2017-18 is 14; and
(v) Number of inappropriate school completed in 2018-19 is 21.
(b) The attached table is a list of completed schools including their the names per province,
(c) the attached table also includes the construction cost for each specified school. The cumulative total is R5,7 Billion
(d) The implementing agents (IA) are also indicted in the attached table. The IA’s are Development Bank of Southern Africa (DBSA), the Independent Development Trust (IDT), the Coega Development Corporation (CDC), the National Department of Public Works (NDPW), the Eastern Cape Provincial Public Works (DPW);
(2) Each school was constructed under the JBCC building contract. Each school was managed according to the said contract. Adjudicated extensions of time were approved where they applied and requisite penalties were levied where applicable.