(1)(a) Since 1 March 2017, 31 Cubans are still in the employ of my Department. 1 Cuban specialist resigned in April 2016 and the other 3 did not renew their contracts when they expired at the end of February 2017.
(1)(b) Their contracts will expire on 21 December 2017 but I have approved that their contracts should be extended up to 30 June 2018.
(2) My Department has not employed any additional Cuban specialists.
(3) The current costs for the financial year under review (2016/17) of contracting the engineers in terms of the line items requested are as follows:
Items |
Cost |
|
(3)(a) |
Salaries |
R 19 132 905.00 |
(3)(b) |
Accommodation |
R 6 414 355.00 |
(3)(c) |
Transport Cost |
R 5 164 250.00 |
(3)(d) |
Other Expenses (Cell phones, 3Gs and S&T claims) |
R 447 080.00 |
TOTAL |
R 31 158 590 |
---00O00---