The road is P1-10 from Ladysmith to Colenso and the maintenance activities are as follows for:
FINANCIAL YEAR 2021-2022
No. |
(a) Budgeted amount |
(b) Detailed work to be carried |
(c) Section of road to be repaired |
(d) Date that work carried out |
(e)(i) Expenditure 2021/22 |
1 |
R 230 338.00 |
Grass cutting |
0 km to 14 km |
June 2021 |
R 230 338 |
2 |
R 161 930.00 |
Installation and repair of Guardrails |
0 km to 7 km |
April 2021 |
R 161 930 |
The internal maintenance team was also involved in the pothole patching on this road throughout the year.
APRIL 2022 TO DATE
No. |
(a) Budgeted amount |
(b) Detailed work to be carried |
(c) Section of road to be repaired |
(d) Date that work carried out |
(e)(ii) Expenditure 1 April 2022 to 31 August 2022 |
1 |
R 153 819.00 |
Line marking |
9 km |
September 2022 |
153 819.00 |
The internal maintenance teams have to date repaired 15 Signs and have repaired a total of 67 m2 of pothole repairs to date.
Future plans
There is allocation for a grass cutting and tree felling contractor to start the works in January 2023 with a total allocated budget of R968 100.00.
Under capital project we have anticipated to Reseal P1-10 for 11 km.