Airports Company South Africa SOC Limited (ACSA)
(1)
(b)Project |
(iii)Estimated Value |
(i)Scope of works |
(ii) Period)Status |
New Realigned Runway |
R 3.8 bn |
The construction of a new code F compliant runway with associated taxiways and ancillary systems |
The tender document preparation phase was concluded and was just issued to the market. |
T2 enablement works T2 Main works |
R 2.8 |
International Terminal expansion including check-in, baggage handling systems and arrivals carousels |
The Enablement Works is currently in the procurement phase with tenders in the market The Main Works is in the detail design phase and will be go through the procurement process during the course of next year |
New Domestic Arrivals |
R 688 mn |
Expansion of the Domestic Arrivals Terminal |
The project will be procured 2-3 months |
Several other smaller projects |
Multiple values |
Aprons, taxiway upgrades and minor terminal expansion |
The projects are in the design development phases and will go through the procurement process during the course of next year |
(2) Falls away.