The Minister of Public Works and Infrastructure
(1)
(a) An assessment was done by day to day works and it was found that Professional engineer must be involved.
(b) It was referred to engineers to conduct an assessment and provide a report. A report has been issued, indicating that the site terrain is approximately 2 kilometers away from the sea. The area has a limited vegetation growth on sandy soil conditions, which insures speedy infiltration due to the large un-compactable voids present. This means that the soil would naturally become over saturated faster than slow infiltration soil types thus creating faster flooding plane. A proper retaining wall will need to be built together with an engineer’s designs.
(2) The Regional Office will only be able to devolve the site, once formal agreement has been reached between DPWI and Department of Defence (DOD) regarding the transfer of custodial functions.
(3)
(a) At this stage, no date has been agreed to regarding the proposed devolution of function.
(b) Prior to custodial devolution taking place, formal agreement/s must be reached between the DPWI and DOD.
(4) No project has been registered for this property.
(5) SANDF has not prioritized any projects for this property.
__________________________
MR. S ZIKALALA, MP
MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE
DATE: