The Minister of Public Works and Infrastructure:
1. (a) ISA was not established as an entity but a function to oversee the implementation of the mandate of Infrastructure. It is part of the National Department of Public Works and Infrastructure (NDPWI) functional organisational structure reporting to the Minister, responsible for PICC & IDMS roles emanating from the National Macro Organisation of Government (NMOG) processes including the urgent need for targeted infrastructure investment.On the 27 May 2020, Cabinet resolved to create Infrastructure South Africa (ISA) to be housed within DPWI to serve the purpose of being a single-entry point and to ensure that DPWI has a system accounting for all infrastructure projects at all levels of government.
(b) Public Service Regulations, 25 (2)(a) states that, based on the strategic plan of the department, an executive authority shall determine the department’s organisational structure in terms of its core mandated and support function. Public Service Act, section 41 stipulates the alignment with the said regulations as well as the role of the Minister of Public Service and Administrations.
(c) The structure depicts ISA at a macro level within the department with the Head of ISA reporting to the Minister of Public Works and Infrastructure.
2. Dr Kgosientsho Ramokgopa is appointed in the Presidency on contract. The Ministerrequested the permission of the Presidency to utilize the expertise of Dr Ramokgopa in introducing the functions of Infrastructure within DPWI.
3. The start-up organisational structure of ISA was concluded by the Minister of Public Works and Infrastructure and submitted to the Minister of Public Service and Administration for his concurrence in accordance with the Public Service Act and Regulations. The organisational has now been approved and ready for implementation.
4. The process of recruitment is currently underway. The positions of Head of ISA, Deputy Director Generals and Chief Directors was advertised on the 8 November 2020.
5. The Department has reprioritised the budget which was approved by National Treasury for an amount of R23.062m. The breakdown is as follows:
a) Compensation of Employees is an amount of R11.943 m
b) Goods and Services is an amount R11.119m
c) And (d) See Annexure A – Allocation letter.