According to the information received from Eskom
(1)
Eskom understands that all future IPP programmes are on hold until such time as the Integrated Resource Plan (IRP) has been concluded.
(1)(a)
Eskom is obliged to implement Government Policy. Should Government instruct Eskom to continue with this programme Eskom will engage on the impact on Eskom and its requirements for the programme.
(2)
Eskom has not agreed to sign the IPP contracts and therefore the Regulation 9 requirements were not assessed by Eskom.
Should Government instruct Eskom to continue with this IPP programme, Eskom will then assess the Power Purchase Agreements against the Regulation 9 requirements of the New Generation Regulations 2011. A matter which requires further clarity and certainty is what constitutes a correct technical risk transfer to the new coal IPP in terms of Regulation 9 of the New Generation Regulations, 2011.