(1)(a)(b) The land belongs to the State.
(2)(a)(i) Planning will commence in the 2018019 financial year and takes approximately 18 months.
(2)(a)(ii) The construction will commence in the second half of the 2019/2020, financial year.
(2)(b) Only once the planning phase (design, specifications, etc.) of such a specialised facility is concluded, will a projected date of completion be known.