1 a) The Houses have not yet been completed, however construction is still underway.
b) i) 41 Houses have been handed over to beneficiaries and they are still 237 houses to be handed over- the delay was due to community unrests which led to the contractor vacating the site. More delays were caused by additional remedial work that had to be done on some of the houses.
ii) We are following engagements between the councillor and the community to resolve any problems that they had with regards to the additional works that have to be done, a submission has been done by the Department of Human Settlements to request additional funding.
2) R 28 241 413.25
3) The contractor was paid all claims for work done and the department does not owe the contractor anything.
4) a) the delays were caused by community unrests which led to the contractors vacating site. More delays were caused by additional remedial works that had to be done on some of the houses and needed extra cost to complete them.
b) June 2021
c) the matter is no longer with both the Former MEC and Former Minister it is with The department of Human Settlements Administration and attending to resolve it. The current Acting Head of Department is addressing the outstanding variations.