(a) The Vulindlela Rural Housing Project commenced in March 2011.
(b) The progress of the project is as follows:
Completed Platforms: 19 490
Completed slabs: 18 413
Completed wall plates: 16 922
Completed Houses: 15 928
Completed Houses with Jojo tanks installed: 15 667
(c) (i) Completed houses: 15 928
(ii) Units occupied: 15 667
(d) Approved Project Budget: R2 587 053 561.62
Expenditure to date: R 1 765 667 534.36
Balance of available Project Budget for MTEF: R821 386 534.36