1. The hospital was completed on 9 March 2022 and is currently operational.
2. (a) The table below reflects the details in this regard:
Contract Name |
Cost |
Contract 1 : Earthworks |
1 244 730,50 |
Contract 2 Pilling |
24 451 211,82 |
Contract 3 Superstructure |
3 172 362 000,79 |
Contract 3 VAT |
475 854 300,12 |
Total |
3 673 912 243,23 |
(b) The original completion date was the 05 October 2018.
(3) (a) 41 Months
(b) Yes there were penalties imposed.
(4) The hospital is operational since August 2021. The practical completion has been following a phased approach until the overall practical completion was reached on 9 March 2022.
(5) (a) Yes
(b) Yes, Operational needs and budget have been catered for
END.