(1) (a) Approximately 7195 units are earmarked for the Birchleigh Ext 4 Project, and the project is not ready to commence with construction at this stage. Information towards implementation will be communicated in due course.
(i) Professional Service Providers have been appointed to start with Detailed Designs which will be completed in June 2019. Construction will only commence in July 2019.
(ii) Three thousand units will be completed in 2021 and the rest in 2023.
(2) The following land uses have been earmarked for the Birchleigh Ext 4 project: