1.
(a) No, construction has not commenced due to budgetary constraints.
(b) The current project status is at feasibility stage and the start date is estimated for 01 April 2020 and completion date is estimated for 20 April 2022.
2.
(a) The estimated start date for the construction of New Birch Acres Primary is 24/10/2017 and the project is on target to commence on the said date.
(b) Construction for Clayville Primary School is estimated to start on 15/02/2020.
(i) Commencement date for New Birch Acres has not changed and for Clayville Primary School start date is 15/02/2020.
(ii) Opening dates cannot be confirmed at this stage; however, the completion dates are estimated for 31 June 2019 for New Birch Acres and 15 May2022 for Clayville Primary School.
Project name |
Project Status |
Date: Start |
Date: Finish |
New Birch Acres Primary School |
Procurement |
24/10/2017 |
31/06/2019 |
Clayville Primary School |
Project Inception |
15/02/2020 |
15/05/2022 |
Esselenpark Primary School |
Feasibility |
01/04/2020 |
20/05/2022 |