a) Synchronisation of Kusile Unit 5:
- Kusile Unit 5 is forecast for first synchronisation in November 2023.
b) Return to operation of all other Kusile units:
- Kusile Unit 4 has been in commercial operation since 31 May 2022, the unit was taken out on a 30 day planned outage and was scheduled to return to service on the 17 September 2023, the unit was returned as planned on 17 September 2023.
- Kusile Units 1 to 3 are forecast to return to operation between October and November 2023
- Kusile Unit 6 is forecast for first synchronisation in August 2024.
Name
|
Date of return
|
1. Kusile 1
|
30 Oct -11 Dec
|
2. Kusile 2
|
30 Nov-24 Dec
|
3. Kusile 3
|
14 Oct-26 Nov
|
4. Kusile 5
|
28 Oct-30 Dec
|