According to Information Received from Eskom:
(a)
The curtailment framework creates capacity by exploiting the intermittent nature of renewable energy resources. Since they are not producing the same energy all the time, more resources can be connected to the grid and for most of the time, the grid capacity will not be exceeded.
Only on rare occasions when the output exceeds grid capacity, will it be necessary to curtail production.
(b)
The comprehensive curtailment framework will be published as soon as all pending matters, such as the compensation mechanism, have been resolved. All matters are expected to be resolved no later than July 2024.