. Medupi is 35% complete, with 56.9% of the budget having being spent. . Kusile is 17% complete, with 30% of the budget having being spent. . Ingula is 41% complete, with 54.3% of the budget having being spent. . The Return-to-Service programme is 93.5% complete, with 89% of the budget having being spent. . Transmission projects are more than 70% complete, with 70.4% of the budget having being spent. . A cooperation agreement between Eskom and Transnet was signed in November 2011 on the development and implementation of a Coal Haulage Road-to-Rail Logistics for Eskom's fleet of coal-fired power stations. . The resulting haulage agreement details the routes and sources of coal to be transported to Eskom powers stations. 3.5.3 Logistics: road, rail and ports