(1) Whether, with reference to Transnet’s New Multi-Product Pipeline from Durban to Gauteng, the planned storage tanks in Durban have been constructed; if not, (a) why not and (b) what (i) are the relevant details of why some or all of these tanks are not being used, (ii) remedial action is required to make the tanks usable and (iii) will the cost of remedial action be; if so, are they being used to full capacity; (2) what are the relevant details of the contractor and/or contractors who have been appointed to (a) construct these tanks or (b) carry out remedial action; (3) what are the costs associated with the construction of these tanks as (a) contracted, (b) constructed to date and (c) an estimated final cost?