The North West Provincial Department of Cooperative Governance, Human Settlements and Traditional Affairs has indicated that the village is known as Ramokokastad which is located in Ward 12 in the area of jurisdiction of the Moses Kotane Local Municipality. Initially, the Peoples Housing Programme project consisted of 200 housing units of which 145 houses were constructed during 2004. In 2005, the National Home Builders Registration Council (NHBRC) required all home builders to enrol building projects and therefore the project was stopped to enable the developers to meet the requirements. However, the developers failed to register as required by the NHBRC and the project was thus not completed.
In June 2019, the Provincial Department appointed a developer to unblock the project and to construct the remaining 55 houses. To date, 52 houses have been completed and the remaining 3 houses are at completion stage of which the installation of ceilings, painting and the clearing of rubble are in progress.