(1) (a) When did construction of the Zola Hospital in Soweto commence, (b) what was the value of the original tender, (c) what are the details of the bidding companies who were shortlisted and (d) which company was awarded the tender; (2) whether the contractor’s services have been suspended; if not, what is the position in this regard; if so, (a) at what stage of the project and (b) why; (3) whether any cancellation fees or penalties had to be paid; if not, how was this conclusion reached; if so, what total amount in fees was paid; (4) whether a new contractor has been appointed to complete the project; if not, why not; if so, what are the relevant details; (5) whether the project has been completed; if not, when is it envisaged to be completed; if so, what total cost was incurred for this project as at the latest specified date for which information is available?