Housing projects are implemented by the Department of Human Settlements in the Municipalities in the Province. The Department of Human Settlements in the Mpumalanga Province was contacted and confirmed the information below as correct.
The Thaba Chweu Local Municipality was contacted to assist with the response to the question. The response is as follows: (Annexure A)
No. |
Project Name |
Financial |
Total Units |
Start Date |
Status |
Budget |
No Allocation |
2014/15 |
n/a |
n/a |
n/a |
n/a |
|
No Allocation |
2015/16 |
n/a |
n/a |
n/a |
n/a |
|
Chryselda |
2016/17 |
200 |
01/11/2016 |
In progress |
R20 600 000 |
|
Mgugwana |
2016/17 |
100 |
01/11/2016 |
Completed (08/12/2017) |
R10 300 000 |
|
Lwakhiti JV |
2017/18 |
150 |
22/09/2017 |
In progress |
R15 450 000 |
|
Fenekwane |
2017/18 |
100 |
22/09/2017 |
In progress |
R10 900 000 |
As per the comments of the Deputy Minister to provide background/ explanatory notes to the matter, the following additional information was obtained.
Housing projects are implemented by the Department of Human Settlements in the Municipalities in the Province. The Department of Human Settlements in the Mpumalanga Province was contacted and confirmed the above information as correct. As implementers of the housing projects, the Department allocates the budget, appoints Service Providers and monitors them in collaboration with the affected Municipality. The Municipality’s responsibilities include the identification of beneficiaries.
2016/17 financial year includes the following: